How to make construction procedures?

>>>Details of the 30-day renovation process

When it comes to decoration, the rookie will be overwhelmed. Decoration is a big project. Xiao Bian specifically arranged the following materials and explained how to formulate the construction sequence.

Residential decoration construction procedures should meet the following rules:

The total construction sequence should be to perform the structural engineering first, then the renovation project, then the installation project, and finally the decoration project.

Residential renovation construction process

(1) Before the residential decoration works, check that the junction drains are unblocked, and the construction of the base body and the basic floor are acceptable.

(2) After the installation of management engineering, electrical wiring, and electrical devices is completed, other decoration works may be carried out.

(3) House decoration works should be carried out according to the following procedures:
→ Fine wood decoration → Paper paste → Electrical installation → Flooring → Paint ceiling paint → Fine wood decoration → Electrical installation → Flooring → Paint

(4) Living room decoration works should be carried out according to the following procedures:
→Detailed decoration → Paste →Electrical installation →Paving floor material →Paint ceiling →Paint →Fine wood decoration →Electrical installation →Paving floor material →Paint

(5) Kitchen decoration works should be carried out according to the following procedures:
Paints → Masonry Platforms → Fine Wood Decorations → Wall Surfaces, Cabinet Applique Tiles → Electrical Appliances, Electric Water Heater Installations → Paving Floor Materials → Paint →
Gas take over.

(6) The bathroom decoration works should be carried out according to the following procedures: ceilings → installation of three large parts (connecting water pipes) → wall surface, bath skirts → baths installation (electrical installations, installations, flooring materials, paints, (7) gas pipelines Installation must be completed by a unit that has a gas installation qualification certificate.


To formulate specific construction procedures, we must also pay attention to the following principles:

The principle of finished product protection: In the cross-operation and parallel operation, the completed decorative works and finished products must take strict protective measures.

The principle of the shortest construction period: the purpose of cross-organization and parallel operations is to shorten the construction period. A basic goal for the construction organization is to complete the project with the fastest speed and design requirements.

The principle of safety: Safety is the basis for generating benefits and guaranteeing the duration.

Ensure key points, make overall arrangements, observe construction deadlines, rationally arrange construction procedures, organize flow construction, and apply advanced science and technology and equipment

Ensure construction safety, reduce engineering costs and improve construction quality.

Home improvement usually includes bricklayers, electricians, plumbers, carpenters, and oil workers.